4010
Install 4" Copper Pipe
- Budgeted
- 360 hrs
- Used
- 150 hrs
- Earned
- 180 hrs
CPI
1.20
Proj. hrs
300
Rate/hr
2.0
360 LF in place. Budget rate 2.0 LF/hr, actual 2.40 LF/hr. Heading 60 hrs under budget.
Driftwood · Consulting for contractors
For self-perform specialty and service contractors, $5M to $75M. Below is exactly what each package shows you, on sample jobs.
Send 10 closed jobs, get a free gain/fade snapshot. Runs in your browser; nothing is uploaded.
Margin Checkup · $500
What it shows
Estimated margin
19.0%
What the bids said
Actual margin
14.2%
What the jobs made
Total fade
$335,400
-4.8 pts on $6,942,000
Jobs that faded
6 of 10
4 gained
Where the profit faded, job by job
Labor carries the fade
| Job | Trade | Contract | Est. margin | Actual | Gain / fade |
|---|---|---|---|---|---|
| Riverside clinic tenant improvement2026-01-16 | Electrical | $486,000 | 19.0% | 13.3% | -$27,600 |
| Harbor Street cold storage2026-02-27 | Electrical | $1,240,000 | 19.0% | 9.8% | -$114,500 |
| Lincoln Elementary lighting retrofit2026-03-13 | Electrical | $318,500 | 20.0% | 22.4% | +$7,700 |
| Westgate apartments, phase 22026-04-30 | Electrical | $2,150,000 | 17.0% | 11.5% | -$118,100 |
| County EOC generator and ATS2026-05-22 | Electrical | $642,000 | 19.0% | 19.7% | +$4,600 |
| Distribution center service contract2026-06-30 | Service | $188,000 | 25.0% | 28.8% | +$7,200 |
| Mercy Hospital MRI suite2026-07-17 | Electrical | $874,000 | 20.0% | 10.6% | -$82,200 |
| Plant 4 switchgear maintenance2026-08-08 | Service | $96,500 | 28.0% | 26.2% | -$1,700 |
| Oak Ridge retail center2026-09-04 | Electrical | $535,000 | 19.0% | 14.8% | -$22,500 |
| Water plant VFD replacements2026-10-02 | Service | $412,000 | 22.0% | 24.8% | +$11,700 |
| All jobs | $6,942,000 | 19.0% | 14.2% | -$335,400 |
Electrical
-$352,600
7 jobs · bid 18.5%, finished 12.9%
Service
+$17,200
3 jobs · bid 23.6%, finished 26.1%
The free snapshot gives you the job view on 10 jobs. The Margin Checkup adds cost types, patterns and the three biggest drivers on 20 to 40.
Field Productivity Setup · $1,000 + $49/mo
What it shows
4010
CPI
1.20
Proj. hrs
300
Rate/hr
2.0
360 LF in place. Budget rate 2.0 LF/hr, actual 2.40 LF/hr. Heading 60 hrs under budget.
4015
CPI
0.79
Proj. hrs
253
Rate/hr
3.0
330 LF in place. Budget rate 3.0 LF/hr, actual 2.36 LF/hr. Heading 53 hrs over budget.
4020
CPI
0.59
Proj. hrs
407
Rate/hr
1.0
165 LF in place. Budget rate 1.0 LF/hr, actual 0.59 LF/hr. Heading 167 hrs over budget.
4030
CPI
1.10
Proj. hrs
109
Rate/hr
1.5
99 EA in place. Budget rate 1.5 EA/hr, actual 1.65 EA/hr. Heading 11 hrs under budget.
CPI is earned hours divided by hours used: above 1.00 the crew is beating the estimate. Projected is budgeted hours divided by CPI. Green is 0.95 and up, orange 0.75 to 0.94, red below 0.75.
| Crew | M2 | T3 | W4 | T5 | F6 | S7 | S8 | M9 | T10 | W11 | T12 | F13 | S14 | S15 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Crew 1 · Mercy East Wing | Submitted | Submitted | Submitted | Submitted | Submitted | No shift | No shift | Submitted | Submitted | Submitted | Submitted | Submitted | No shift | No shift |
| Crew 2 · Mercy East Wing | Submitted | Submitted | Submitted | Submitted | Missed | No shift | No shift | Submitted | Submitted | Submitted | Submitted | Submitted | No shift | No shift |
| Crew 3 · Westgate Ph. 2 | Submitted | Submitted | Submitted | Submitted | Submitted | No shift | No shift | Submitted | Submitted | Submitted | Submitted | No shift | No shift | No shift |
| Crew 4 · Harbor Cold Storage | Submitted | Missed | Submitted | Submitted | Missed | No shift | No shift | Missed | Submitted | Submitted | Missed | Missed | No shift | No shift |
| Crew 5 · Water Plant VFDs | Submitted | Submitted | Submitted | Submitted | Submitted | No shift | Submitted | Submitted | Submitted | Submitted | Submitted | Submitted | No shift | No shift |
| Service · Plant 4 | Submitted | Submitted | Submitted | Submitted | Submitted | No shift | No shift | Submitted | Submitted | Submitted | Submitted | Submitted | No shift | No shift |
Submitted Missed· No shiftCrew 4 missed 5 days: Harbor is also the job running red.
The square is the shop. A diagram, not a street map: distance and direction only.
Operations Assessment · $5,000 + $299/mo
What you get
About $1,020,000 a year in margin at stake, most of it in two fixes.
| When | Action | Owner | How we know it worked |
|---|---|---|---|
| Weeks 1–2 | Start a same-day change log on every job | PMs | Changes logged within 24 hours |
| Weeks 2–4 | Weekly pacing on the top 10 cost codes, three pilot jobs | Field ops | Crews submitting 5 of 5 days |
| Weeks 4–8 | Reset estimating labor rates from closed jobs | Chief estimator | New rates in every bid after week 8 |
| Weeks 8–12 | Monthly margin review: forecast vs. pace, every job | Owner + PMs | Fade caught before 50% complete |
Then monthly: one working session, a review of margin and pacing numbers against this plan, and help putting the fixes in place.
The assessment includes a gain/fade analysis like the one above, and the monthly advisor reviews your margin and pacing numbers with you.
Packages
Fixed prices, stated up front
$500One time
Where did the profit go on the jobs you already finished?
About two weeks from receiving your data
Request this$1,000+ $49/moSetup, then monthly
Is this week's crew on pace, or will you find out at closeout?
Four to six weeks to set up
Request this$5,000+ $299/moAssessment, then monthly
Where is the business leaking margin, from bid to final bill?
Four to six weeks for the assessment
Request thisNot sure which fits? Start with a 30-minute call. No pitch: if none of these is right for you, we will say so.
How it works
Start free, decide later
Put 10 closed jobs in the template and see your gain/fade in the browser. Two minutes, nothing uploaded.
We look at the snapshot together and agree whether a package fits. If it does not, we say so.
Job cost and estimate reports straight from the system you already use. No new software to install.
Plain language, your numbers, and a short list of fixes ranked by dollars.
Questions
Straight answers
Self-perform specialty and service contractors doing roughly $5M to $75M a year: electrical, mechanical, plumbing, fire protection, concrete, interiors, and similar trades. If you carry your own field labor, gain/fade and production pacing apply to you.
The difference between the margin you estimated on a job and the margin you actually made. Fade is profit that slipped away between the bid and the closeout. Gain is the opposite. Looking across many closed jobs shows where it keeps happening.
Nothing leaves your computer. The snapshot reads your file and does the math in your browser. It is not uploaded, stored, or sent to us. If you then send a request, you can choose to include the summary totals (no job names).
Exports from your job cost and estimating systems for 20 to 40 closed jobs: contract value with change orders, the estimate, and actual cost by cost type (labor hours and dollars, material, subs, equipment). Excel or CSV exports from Foundation, Viewpoint, Sage, Spectrum, QuickBooks and similar systems all work.
It is used only for your engagement, shared the way you choose, and deleted when the work is done if you ask. We will sign your NDA.
No. We work from the systems and spreadsheets you already have. The Field Productivity monthly fee covers hosting the pacing report, updating rates and support.
It does the tedious part: cleaning exports, matching cost codes, and sorting through hundreds of rows to find patterns. People check the work and make the calls. You get findings, not a chatbot.
No. They run month to month and you can stop with 30 days' notice.
Same team. The club stays free and open, members are never pitched, and nobody pays for coverage in the Power Brief. Consulting is for contractors who ask for it.
Free · Two minutes · Nothing uploaded