You bid the margin. See where it went.

For self-perform specialty and service contractors, $5M to $75M. Below is exactly what each package shows you, on sample jobs.

Send 10 closed jobs, get a free gain/fade snapshot. Runs in your browser; nothing is uploaded.

1A

Margin Checkup · $500

What it shows

Every closed job, estimate against actual. And why it faded.

Estimated margin

19.0%

What the bids said

Actual margin

14.2%

What the jobs made

Total fade

$335,400

-4.8 pts on $6,942,000

Jobs that faded

6 of 10

4 gained

Fade by job10 closed jobsSample data

Where the profit faded, job by job

  • Westgate apartments, phase 2-$118,100 · -5.5 pts
  • Harbor Street cold storage-$114,500 · -9.2 pts
  • Mercy Hospital MRI suite-$82,200 · -9.4 pts
  • Riverside clinic tenant improvement-$27,600 · -5.7 pts
  • Oak Ridge retail center-$22,500 · -4.2 pts
  • Plant 4 switchgear maintenance-$1,700 · -1.8 pts
  • County EOC generator and ATS+$4,600 · +0.7 pts
  • Distribution center service contract+$7,200 · +3.8 pts
  • Lincoln Elementary lighting retrofit+$7,700 · +2.4 pts
  • Water plant VFD replacements+$11,700 · +2.8 pts
Dollars of profit gained or faded against the estimate, and the change in margin points. Your data, figured in your browser.
Fade by cost typeSame 10 jobsSample data

Labor carries the fade

  • Labor-$268,900

    Labor ran over on every job that faded

  • Material-$41,300

    Copper and gear price moves after bid

  • Subcontractors-$38,700

    Low-voltage and trenching subs over their quotes

  • Equipment+$6,200

    Lift rentals came in under budget

  • General conditions+$7,300

    Shorter durations on service work

Fade to the left, gain to the right, one dollar scale. Sample data.
Patterns it revealsSample data
  1. Labor is 77% of the fade. Material and subs together are under a quarter.
  2. Jobs over $800K lost 7.4 margin points; smaller jobs lost 0.8. Big jobs are where the estimate's labor rates break.
  3. Service work beat its estimate: bid 23.6%, finished 26.1%. The fade is a project problem, not a company-wide one.
Open the job table · 10 jobs

Every job

JobTradeContractEst. marginActualGain / fade
Riverside clinic tenant improvement2026-01-16Electrical$486,00019.0%13.3%-$27,600
Harbor Street cold storage2026-02-27Electrical$1,240,00019.0%9.8%-$114,500
Lincoln Elementary lighting retrofit2026-03-13Electrical$318,50020.0%22.4%+$7,700
Westgate apartments, phase 22026-04-30Electrical$2,150,00017.0%11.5%-$118,100
County EOC generator and ATS2026-05-22Electrical$642,00019.0%19.7%+$4,600
Distribution center service contract2026-06-30Service$188,00025.0%28.8%+$7,200
Mercy Hospital MRI suite2026-07-17Electrical$874,00020.0%10.6%-$82,200
Plant 4 switchgear maintenance2026-08-08Service$96,50028.0%26.2%-$1,700
Oak Ridge retail center2026-09-04Electrical$535,00019.0%14.8%-$22,500
Water plant VFD replacements2026-10-02Service$412,00022.0%24.8%+$11,700
All jobs$6,942,00019.0%14.2%-$335,400

By trade

  • Electrical

    -$352,600

    7 jobs · bid 18.5%, finished 12.9%

  • Service

    +$17,200

    3 jobs · bid 23.6%, finished 26.1%

The free snapshot gives you the job view on 10 jobs. The Margin Checkup adds cost types, patterns and the three biggest drivers on 20 to 40.

1B

Field Productivity Setup · $1,000 + $49/mo

What it shows

Know by Wednesday if a crew is behind. Not at closeout.

Cost code cards: budgeted, used and earned hours

Mercy Hospital East Wing · cost codesJob 24-118 · Week 6 of 14Sample data
  • 4010

    Install 4" Copper Pipe

    On pace
    Budgeted
    360 hrs
    Used
    150 hrs
    Earned
    180 hrs

    CPI

    1.20

    Proj. hrs

    300

    Rate/hr

    2.0

    360 LF in place. Budget rate 2.0 LF/hr, actual 2.40 LF/hr. Heading 60 hrs under budget.

  • 4015

    Insulation Wrap

    Watch
    Budgeted
    200 hrs
    Used
    140 hrs
    Earned
    110 hrs

    CPI

    0.79

    Proj. hrs

    253

    Rate/hr

    3.0

    330 LF in place. Budget rate 3.0 LF/hr, actual 2.36 LF/hr. Heading 53 hrs over budget.

  • 4020

    Underground Drainage

    Behind
    Budgeted
    240 hrs
    Used
    280 hrs
    Earned
    165 hrs

    CPI

    0.59

    Proj. hrs

    407

    Rate/hr

    1.0

    165 LF in place. Budget rate 1.0 LF/hr, actual 0.59 LF/hr. Heading 167 hrs over budget.

  • 4030

    Hangers and Supports

    On pace
    Budgeted
    120 hrs
    Used
    60 hrs
    Earned
    66 hrs

    CPI

    1.10

    Proj. hrs

    109

    Rate/hr

    1.5

    99 EA in place. Budget rate 1.5 EA/hr, actual 1.65 EA/hr. Heading 11 hrs under budget.

CPI is earned hours divided by hours used: above 1.00 the crew is beating the estimate. Projected is budgeted hours divided by CPI. Green is 0.95 and up, orange 0.75 to 0.94, red below 0.75.

The foreman's daily log. No login, about a minute.

Foreman daily logPhone · no loginSample data
Daily productionTue 10 Nov

Mercy Hospital East Wing

Crew 1 · opened from a text link

4010 Install 4" Copper Pipe
4015 Insulation Wrap
4020 Underground Drainage

About 60 seconds a day

Who sent their log, the last 14 days

Submission pulse · last 14 days54 of 60 logs · 90%Sample data
Daily production logs submitted per crew over 14 days, 2 to 15 November 2026 (sample data)
CrewM2T3W4T5F6S7S8M9T10W11T12F13S14S15
Crew 1 · Mercy East WingSubmittedSubmittedSubmittedSubmittedSubmittedNo shiftNo shiftSubmittedSubmittedSubmittedSubmittedSubmittedNo shiftNo shift
Crew 2 · Mercy East WingSubmittedSubmittedSubmittedSubmittedMissedNo shiftNo shiftSubmittedSubmittedSubmittedSubmittedSubmittedNo shiftNo shift
Crew 3 · Westgate Ph. 2SubmittedSubmittedSubmittedSubmittedSubmittedNo shiftNo shiftSubmittedSubmittedSubmittedSubmittedNo shiftNo shiftNo shift
Crew 4 · Harbor Cold StorageSubmittedMissedSubmittedSubmittedMissedNo shiftNo shiftMissedSubmittedSubmittedMissedMissedNo shiftNo shift
Crew 5 · Water Plant VFDsSubmittedSubmittedSubmittedSubmittedSubmittedNo shiftSubmittedSubmittedSubmittedSubmittedSubmittedSubmittedNo shiftNo shift
Service · Plant 4SubmittedSubmittedSubmittedSubmittedSubmittedNo shiftNo shiftSubmittedSubmittedSubmittedSubmittedSubmittedNo shiftNo shift

Submitted Missed· No shiftCrew 4 missed 5 days: Harbor is also the job running red.

Every job on one radar, colored by pace

Jobsite radar · all active jobs7 jobs · 8 crewsSample data
Jobsite radar, sample dataSeven jobs plotted by direction and distance from the shop, colored by pace. The list beside the map has the details.10 mi20 mi30 miN1234567
  1. Mercy Hospital East Wing9 mi · 2 crewsCPI 0.92Watch
  2. Westgate Apartments Ph. 217 mi · 1 crewCPI 1.04On pace
  3. Harbor Cold Storage24 mi · 1 crewCPI 0.71Behind
  4. Water Plant VFDs28 mi · 1 crewCPI 1.12On pace
  5. Plant 4 Service6 mi · 1 crewCPI 1.01On pace
  6. Oak Ridge Retail31 mi · 1 crewCPI 0.84Watch
  7. Lincoln Elementary21 mi · 1 crewCPI 0.98On pace

The square is the shop. A diagram, not a street map: distance and direction only.

1C

Operations Assessment · $5,000 + $299/mo

What you get

Where the business leaks margin, ranked by dollars, with a plan.

Operations Assessment · reportSample Mechanical Co. · $28M · 140 field staffSample data

1 · Scorecard

  • Estimating3/5
    Labor rates last updated in 2023
  • Project management2/5
    No mid-job forecast; WIP is a guess
  • Field productivity2/5
    Quantities never tracked against hours
  • Change orders2/5
    31% of field changes never priced
  • Billing and cash4/5
    Bills on time; retention slow to collect
  • Data and systems3/5
    Good job cost data, little use of it

2 · Findings, ranked by dollars

About $1,020,000 a year in margin at stake, most of it in two fixes.

  1. Unpriced field changes$410,000/yr

    Fix: Same-day change log and a weekly pricing review

  2. Labor overruns found at closeout$360,000/yr

    Fix: Weekly unit-rate pacing on the top 10 cost codes

  3. Stale estimating labor rates$190,000/yr

    Fix: Reset rates from 24 months of closed-job actuals

  4. Slow retention collection$60,000/yr

    Fix: Closeout checklist tied to the final pay app

3 · The 90-day plan

Sample 90-day plan with timing, action, owner and measure
WhenActionOwnerHow we know it worked
Weeks 1–2Start a same-day change log on every jobPMsChanges logged within 24 hours
Weeks 2–4Weekly pacing on the top 10 cost codes, three pilot jobsField opsCrews submitting 5 of 5 days
Weeks 4–8Reset estimating labor rates from closed jobsChief estimatorNew rates in every bid after week 8
Weeks 8–12Monthly margin review: forecast vs. pace, every jobOwner + PMsFade caught before 50% complete

Then monthly: one working session, a review of margin and pacing numbers against this plan, and help putting the fixes in place.

The assessment includes a gain/fade analysis like the one above, and the monthly advisor reviews your margin and pacing numbers with you.

1D

Packages

Fixed prices, stated up front

Packages

Not sure which fits? Start with a 30-minute call. No pitch: if none of these is right for you, we will say so.

1E

How it works

Start free, decide later

How it works

  1. Try the free snapshot

    Put 10 closed jobs in the template and see your gain/fade in the browser. Two minutes, nothing uploaded.

  2. Talk for 30 minutes

    We look at the snapshot together and agree whether a package fits. If it does not, we say so.

  3. Send the exports

    Job cost and estimate reports straight from the system you already use. No new software to install.

  4. Get findings you can act on

    Plain language, your numbers, and a short list of fixes ranked by dollars.

1F

Questions

Straight answers

Frequently asked questions

Who is this for?

Self-perform specialty and service contractors doing roughly $5M to $75M a year: electrical, mechanical, plumbing, fire protection, concrete, interiors, and similar trades. If you carry your own field labor, gain/fade and production pacing apply to you.

What is gain/fade?

The difference between the margin you estimated on a job and the margin you actually made. Fade is profit that slipped away between the bid and the closeout. Gain is the opposite. Looking across many closed jobs shows where it keeps happening.

What happens to the data I put in the free snapshot?

Nothing leaves your computer. The snapshot reads your file and does the math in your browser. It is not uploaded, stored, or sent to us. If you then send a request, you can choose to include the summary totals (no job names).

What data do you need for the full Margin Checkup?

Exports from your job cost and estimating systems for 20 to 40 closed jobs: contract value with change orders, the estimate, and actual cost by cost type (labor hours and dollars, material, subs, equipment). Excel or CSV exports from Foundation, Viewpoint, Sage, Spectrum, QuickBooks and similar systems all work.

How is my data handled on paid work?

It is used only for your engagement, shared the way you choose, and deleted when the work is done if you ask. We will sign your NDA.

Do I have to buy software?

No. We work from the systems and spreadsheets you already have. The Field Productivity monthly fee covers hosting the pacing report, updating rates and support.

Where does AI come in?

It does the tedious part: cleaning exports, matching cost codes, and sorting through hundreds of rows to find patterns. People check the work and make the calls. You get findings, not a chatbot.

Are the monthly plans a long contract?

No. They run month to month and you can stop with 30 days' notice.

How does this relate to Driftwood Club?

Same team. The club stays free and open, members are never pitched, and nobody pays for coverage in the Power Brief. Consulting is for contractors who ask for it.

Free · Two minutes · Nothing uploaded

Send 10 closed jobs. Get a free gain/fade snapshot.

Try the free snapshot